← Back to Archive
Our Office JudgmentcommercialMarch 21st, 2025

A Villa's Foundation of Disputes: Court Untangles Shared Blame in Construction Standoff

Abu Dhabi Commercial Court of First Instance, Sixth Simple Commercial Circuit

A Dream Villa Turns into a Legal Battlefield

A dispute that began with the ambitious construction of a private villa in Abu Dhabi has culminated in a detailed court ruling, untangling a complex web of claims and counterclaims involving the property owner, the main contractor, and the project's engineering consultant. The Abu Dhabi Commercial Court of First Instance meticulously dissected the project's failings, ultimately concluding that both the owner and the contractor shared responsibility for the significant delays that plagued the construction, and issued a judgment that balanced the financial obligations of all parties involved.

Background of the Dispute: A Project Derailed

In late 2021, a property owner entered into a lump-sum contract worth approximately AED 2.76 million with a general contracting company to build a residential villa in Abu Dhabi's Al Shawamekh district. The project, with a 16-month timeline, was scheduled for completion in early 2023. However, as the construction neared its final stages, the relationship between the parties soured dramatically.

The contractor initiated legal proceedings, alleging that the owner had breached their contractual duties. They claimed to have completed all agreed-upon work without delay, but faced significant obstruction from the owner who, they argued, withdrew certain project items and was slow to provide necessary approvals. The core of the contractor's complaint was the owner's refusal to sign off on the final blueprints with the engineering consultant, a step required to obtain the building completion certificate. This refusal, the contractor claimed, was a tactic to avoid paying the final installment of AED 545,387. The contractor sought payment of this amount, along with AED 50,000 in damages and the release of their project bank guarantee.

The Owner's Counter-Offensive

In response, the villa owner filed a robust counterclaim, not only denying the contractor's allegations but also introducing the project's engineering consultant as a third party to the dispute. The owner painted a different picture, one of a contractor who was slow, delivered defective work, and ultimately caused the project's delay. His counterclaim sought over AED 564,000 from the contractor, which included:

  • AED 276,098 in delay penalties.

  • AED 170,000 as compensation for having to rent an alternative residence.

  • AED 118,734.5 to cover the difference in material costs.

Furthermore, the owner accused the consultant of failing in their supervisory duties and sought the termination of their contract and a refund of 10% of the supervision fees. The consultant, now drawn into the legal fray, filed their own ancillary claim against both the owner and the contractor for unpaid professional fees amounting to nearly AED 98,500.

The Expert's Verdict: A Case of Shared Fault

Faced with conflicting narratives, the court appointed an independent engineering expert to investigate the project and determine the true state of affairs. The expert's report became the cornerstone of the court's final judgment. After a thorough review of the site, contracts, and correspondence, the expert concluded that neither party was blameless. The delays were a result of a series of mutual failings:

  • The Contractor's Faults: The expert noted that there was a demonstrable slowness in the pace of work, identified several defects in the completed works, and confirmed that the contractor had, at one point, locked the owner and consultant out of the project site.

  • The Owner's Faults: The expert found that the owner contributed significantly to the delays through late payments and approvals, using external labor on the site (or commissioning the contractor's labor directly), tardiness in making decisions on interior decor, and, crucially, refusing to sign the final drawings required for project completion.

The expert's impartial assessment was that both parties were equally responsible for the project's derailment. Financially, the report calculated that the net amount owed by the owner to the contractor, after accounting for defects and unfinished work, was AED 341,538.

The Court's Final Judgment

Adopting the expert's comprehensive report, the court delivered a nuanced and balanced decision.

The Original Claim (Contractor vs. Owner)

The court ordered the owner to pay the contractor the expert-verified amount of AED 341,538, along with 3% annual interest. The contractor's claim for additional damages was rejected, as the court held that their own contribution to the delays disqualified them from receiving compensation. However, the court did order the release of the contractor's AED 200,000 performance bond.

The Counterclaim (Owner vs. Contractor & Consultant)

The court systematically dismantled the owner's counterclaim. The demand for delay penalties was dismissed based on a critical legal principle: such penalties are only enforceable when a project is fully completed and handed over late. Since the project was only 97.11% complete, the claim was invalid. The claims for material costs and rent were also rejected because the owner's own actions were a direct cause of the delays. The court did, however, grant the owner's request for the contractor to provide all payment invoices. The owner's case against the consultant also collapsed, as the expert found their supervision to be adequate. The owner was ordered to bear the legal costs for this failed claim.

The Ancillary Claim (Consultant vs. Owner & Contractor)

The court upheld the consultant's claim for unpaid fees. Based on the expert's calculations, the court ordered the owner to pay the consultant AED 30,188 and ordered the contractor to pay the consultant AED 13,125, holding both parties accountable for their respective outstanding dues, plus 3% annual interest.

Ultimately, the judgment served as a powerful reminder that in complex construction contracts, responsibility is a two-way street. The court's reliance on a neutral expert allowed it to look past the accusations and establish a fair resolution based on the documented failures of all parties involved.

ID: a76e9eb2...