← Back to Archive
Our Office JudgmentcommercialOctober 23rd, 2025

The Unfinished Villa: Court Untangles Complex Construction Dispute, Citing Mutual Fault for Delays

Abu Dhabi Commercial Court of First Instance

Unfinished Dreams: A Construction Contract Dispute Over a Luxury Villa

A dream to build a luxury villa in Abu Dhabi devolved into a complex legal battle involving a construction contractor, a property owner, an engineering consultant, and a major financing bank. The Abu Dhabi Commercial Court of First Instance was tasked with untangling a web of claims and counterclaims centered on project delays, unpaid dues, and breach of contract, ultimately delivering a nuanced verdict that held both the contractor and the owner partially responsible for the project's derailment.

📋 The Foundation of the Dispute: The Villa Contract

The story began when a property owner entered into a significant construction agreement with a general contracting company to build a two-story villa with a rooftop, an attached council (majlis), an electrical room, and a boundary wall. The total value of the contract was set at a substantial AED 3,200,000. This price included the fees for the engineering consultant hired to oversee the project but excluded the Value Added Tax (VAT).

The financing was structured through a combination of a government housing loan of AED 2,000,000, managed by a prominent local bank, and a direct contribution of AED 1,200,000 from the owner, in addition to the VAT. The project timeline was strictly defined, with a completion period of 17 months from the official commencement date.

⚡ Cracks in the Project: Allegations and Lawsuits

As construction progressed, the relationship between the parties soured. The contractor, alleging significant financial losses, initiated legal proceedings. The company claimed that while it had completed all work funded by the owner's direct contribution (100%) and a significant portion of the bank-financed work (78%), it was still owed a substantial amount. The contractor filed a lawsuit against the owner, the consultant, and the financing bank, demanding:

  • Payment of AED 1,118,898 for original and variation works, as well as price differences.

  • An additional AED 200,000 in compensatory damages for material losses.

  • A statutory interest of 9% per annum from the date of filing until full settlement.

The contractor argued that the project delays were primarily caused by the owner, who allegedly delayed approvals for plans and unilaterally withdrew certain work items from the contract's scope, disrupting the workflow and project timeline. The consultant was accused of failing to properly manage the project and ensure timely payments.

🔍 The Counter-Offensive: Claims from the Owner and Consultant

The property owner vehemently denied these allegations and launched a counterclaim. He contended that the contractor was the one who breached the agreement and caused delays. The owner sought:

  • Payment of AED 500,000, which he claimed was owed to him based on a settlement agreement.

  • The return of three cheques totaling AED 324,904.

  • Compensation of AED 175,096 for damages incurred.

Adding another layer to the dispute, the engineering consultant also filed a counterclaim, but against the contractor. The consultant demanded AED 60,000, citing an agreement where the contractor had committed to paying a monthly penalty of AED 2,500 for delays in project completion.

⚖️ The Court's Expert Intervention and Findings

Faced with conflicting technical and financial claims, the court appointed an independent engineering expert to conduct a thorough investigation. The expert's mandate was to review the contract, inspect the site, analyze all financial records, determine the percentage of work completed, and assign responsibility for the delays. After extensive review and meetings with all parties, the expert submitted a comprehensive report that became the cornerstone of the court's final judgment.

The expert concluded:

  • Financial Reckoning: The total value of the work executed by the contractor amounted to AED 2,974,086. The total payments made by the owner and the bank were AED 2,740,417. This left a net balance of AED 233,669 payable to the contractor.

  • Shared Responsibility for Delays: Crucially, the expert found that both parties had contributed to the project's failure to complete on time. The contractor had delayed in execution, while the owner had also caused delays by withdrawing work items and managing them through other subcontractors, which disrupted the project's critical path.

  • Consultant's Fees: The expert verified the contractor's commitment to pay delay penalties to the consultant. Calculating the delay period at 17 months, the expert determined the amount owed to the consultant was AED 42,500 (17 months x AED 2,500).

  • Other Obligations: The contractor was obligated to provide the owner with the necessary tax invoices for the completed work to enable VAT recovery.

🏛️ The Final Verdict

The court adopted the expert's report in its entirety, finding its conclusions to be well-founded and based on a sound examination of the evidence. The final judgment meticulously addressed each claim and counterclaim.

For the Original Lawsuit (Contractor vs. Owner):

  • The owner was ordered to pay the contractor the outstanding amount of AED 233,669.

  • A reduced annual interest rate of 2% was applied from the date the case was filed.

  • The owner was ordered to return the three cheques totaling AED 324,904, as per a previous settlement.

  • The contractor's claim for AED 200,000 in damages was rejected, as the court found mutual fault for the delays.

For the Counterclaim (Owner vs. Contractor):

  • The contractor was ordered to provide the owner with all official tax invoices.

  • All other financial and compensation claims made by the owner were dismissed.

For the Counterclaim (Consultant vs. Contractor):

  • The contractor was ordered to pay the engineering consultant AED 42,500 for the accrued delay penalties.

Finally, the court dismissed the case against the financing bank, ruling that it had no direct involvement in the construction dispute between the other parties. The judgment serves as a clear reminder that in complex construction disputes, courts heavily rely on technical expertise and that contractual commitments, including penalties, will be enforced, while claims for damages may be nullified by shared responsibility.

ID: cc38f661...